GV-14 (I-41 to Lawrence Drive) 2025 Construction (Brown County Project website)

Anticipated Schedule:

Stage Anticipated Start Anticipated Completion Description
1 March 31 April 28 Remove raised lane divider in preparation for Stage 2. Minimal traffic impacts.
2 April 28 July 3 See Stage 2 Overview Plan. Construction of Roundabout. Hard closure with traffic restrictions. Lawrence Drive to the north and Southbridge to the east to be closed.
3 July 3 August 27 See Stage 3 Overview Plan. Construction of Roundabout. Hard closure with traffic restrictions. Lawrence Drive to the south to be closed.
4 September 15 Final items to complete GV-14 work. No traffic restrictions anticipated.

PIM Exhibit Road Layout

Construction Staging

Stage 2 Overview Plan

Stage 3 Overview Plan

Detour Route/Traffic Control by stages

Detour Route/Traffic Control for Business Access by stages